SANRAL and its construction partners teamed up at a cost of R1.4m to address the youth unemployment crisis in Malmesbury, which is on the N7. 22 learners received certificates for completing NQF Level 3 and 10 for NQF Level 4. These were all focused on various construction disciplines.
The four haul roads for the N2 West Coast Road Project are close to completion. They will facilitate the movement of materials, equipment, machinery and workers to the Msikaba and Mtentu bridge projects. They are essential support structures for these major bridges which require specialised engineering skills and building techniques.
All construction on the R573 Moloto Road is shut down for the December holidays but will resume on 8 January 2018. Routine road maintenance work went on uninterrupted. The road will be open to traffic during the shut-down period. Progress on the upgrade is on schedule.